Decision Maker: Deputy Chief Executive and Director for Corporate Services, Director for Children and Families
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
For the Director for Children and Families and
Deputy Chief Executive and Director for Corporate Services, in
consultation with the Cabinet Member for Education (and SEND) to
enable the ATS option to proceed by entering into relevant legal
agreements with Rugeley Power Limited (RPL), Lichfield and Cannock
Chase District Councils, Department for Education (DfE) and Homes
England
Approval is sought for a Deed of Variation and
relevant legal agreements to enable the county council to elect, or
not, for the ATS by Wednesday 31 May 2023.
Background
1. On Wednesday 15 March 2023, in an exempt report to Cabinet,
support was given to deliver an All Through School (ATS) on the
former Rugeley power station site, subject to the approval of
relevant legal agreements.
2.Cabinet was advised of the permanent shortfall of secondary
school places in Rugeley following The Hart’s decision to
close the Hagley Park site.
3.To remedy the shortfall, increase local choice and provide future
capacity for over 2,000 homes on the former power station site,
John Taylor Multi Academy Trust (JTMAT) had successfully applied to
the DfE to open an All Through School (ATS) on the site.
4.To secure delivery of the ATS, changes are required to the
current Section 106 agreement with the site owner, Rugeley Power
Limited, through a “Deed of Variation” (DoV) and other
legal agreements.
5.Cabinet agreed to delegate authority to the Director for Children
and Families and Deputy Chief Executive and Director for Corporate
Services, in consultation with the Cabinet Member for Education
(and SEND), to enter into relevant legal agreements to allow the
All Through School (ATS) option to proceed.
Legal agreements
6.Officers have now completed detailed, sensitive and confidential
negotiations on a DoV and relevant agreements, which are agreed by
all parties.
7.If agreed, and subject to planning approval, the agreements would
enable the ATS to be constructed by the DfE. Whilst the timescale
is challenging, the target opening date would be September 2025.
Each September, the ATS would admit into nursery, reception and
Year 7 and by September 2031 there were children in every year
group. Its total capacity would be 52 nursery places, 420 primary
places and 750 secondary places and 200 post-16 places.
8.If agreed by all parties , the DoV, which would enable SCC to
elect for the ATS by no later than 31 May 2023. Upon election for
the ATS, the DoV would oblige the site owner to:
a.transfer ownership of the site for the ATS and Shared Sports
Facilities to SCC;
b.contribute £13.9m, in instalments, towards the cost of
construction of the ATS and Shared Sports Facilities;
c.contribute £1.4m, in instalments, towards the cost of a new
access from the public highway;
d. provide access road from the public highway, and all services,
to the ATS site.
9.Legal agreements would enable, subject to planning
permission:
a. DfE to construct the ATS and Shared Sport Facilities at an
estimated cost of c£39m. DfE would fund c£25m, the site
owner would contribute £13.9m and the county council would
contribute £1m;
b.county council to construct a new access from the public highway
(in part by acquiring a small area of land from Homes England at no
cost). The site owner would contribute £1.4m and the county
council would contribute up to c£1m.
c. As usual, the county council would enter into a 125-year lease
with the academy trust. JTMAT.
d. Responsibility for securing the operation of the Shared Sport
Facilities on the ATS site would transfer from the site owner to
county council.
10.Table 1 shows the county council’s capital contribution of
circa £2m towards the ATS, Shared Sport Facilities and
associated infrastructure.
Options considered
11.Under the current section 106 agreement, the site owner would
contribute £7.9m and a site for a primary school. The site
owner would provide an £8.0m contribution towards the
provision of secondary places off-site, which would most likely
require the reopening of Hagley Park High School as an
academy.
12.Without the DoV, Table 2 shows a county council’s capital
contribution of circa £11.6m towards a primary school and
refurbished Hagley Park. It shows that, without an ATS,
Staffordshire would lose circa £24.5m of funding from
DfE.
13.From an educational perspective, in March, Cabinet concluded
that the ATS would be a better outcome. Reopening the old Hagley
Park site would be more expensive, have less facilities and be less
popular with families, which may affect its financial and
educational viability.
Publication date: 16/06/2023
Date of decision: 23/05/2023